Projects Hydro

MBH is proud to have massive installations at the worlds 2nd longest Dam site. Our pumps are mainly used for dewatering from the gates during rainy seasons, as well as used to dewatering excess water from catchment areas on a dam site.

steel

Projects

Sardar sarovar Narmada nigam LTD

  • Number of pumps supplied - 22
  • total capacity installed – 1850 HP
  • Largest pump in the fleet  - 100 HP
  • head range – 50 MTR
  • flow range – 250 M3/HR
  • application – Dewatering water

Alaknanda Hydro power company limited

  • Number of pumps supplied - 4
  • total capacity installed – 400 HP
  • Largest pump in the fleet  - 100 HP
  • head range –  36 MTR
  • flow range –  450 M3/HR
  • application – Dewatering water

Orissa hydro power corporation ltd
( Burla power Station )

  • Number of pumps supplied - 2
  • total capacity installed –300 HP
  • Largest pump in the fleet  - 150 HP
  • head range – 60 MTR
  • flow range –   M3/HR
  • application – Dewatering water

Sardar sarovar Narmada nigam LTD

  • Number of pumps supplied - 18
  • total capacity installed – 315 HP
  • Largest pump in the fleet  - 50 HP
  • head range – 25 MTR
  • flow range –   2000 M3/HR. ( 540 RPM pumps )
  • application – Dam Dewatering water

Nepal Electricity Authority ( Nepal )

  • Number of pumps supplied - 1
  • total capacity installed –135 HP
  • Largest pump in the fleet  - 135 HP
  • head range – 15 MTR
  • flow range –   1460 M3/HR
  • application – Dam Dewatering water